Corven & Ashby, cost and risk advisory

Allowance reconciliation, and the money that never comes back

Contingency and allowances

Allowance reconciliation is the step where every allowance in the contract is compared to what was actually spent, and the difference is settled. In principle an underspent allowance returns to the owner. In practice, on most projects, very little comes back, and the reasons are all in the contract.

What an allowance is, and what it is not

An allowance is a sum carried in the contract for scope that is known to exist but not yet defined well enough to price. Elevator finishes, signage, landscape, specialty equipment, the graphics package.

It is a placeholder, not a price. The contractor has not promised that the work costs that much. The contractor has promised to carry that amount and to reconcile against actual cost.

Which means every allowance is an open commercial position for the life of the project, and the sum of them on a normal commercial building is commonly between three and eight percent of the contract value.

Owners usually understand the upside risk. An allowance set below what the work will cost produces a change order, and that is the subject of allowance management.

The downside is less discussed and is worth real money. Allowances are frequently set generously, work frequently costs less than the allowance carried, and on a job with forty allowances some of them will underspend.

Whether the owner ever sees that money is a question of four contract provisions.

The four mechanisms that stop allowance reconciliation

Netting. Where the contract permits overruns on one allowance to be offset against underruns on another, the reconciliation happens inside the allowance pool and the owner sees only the net. Since allowances are set by the same estimator with the same tendencies, the pool nets to roughly zero and nothing returns.

Transfer to contingency. Where an underspent allowance can be moved to the contractor contingency, it leaves the allowance schedule and enters a fund with different rules and less visibility.

Absorption into the savings pool. Where the underrun simply becomes part of the final cost of the work calculation, it is shared at the shared savings percentage rather than returned in full, which on a fifty percent split means half of it stays.

Definition of the allowance scope. The broadest allowances are the hardest to reconcile. An allowance for signage that does not say which signs is spent on whatever signage was installed, and an underrun is impossible to demonstrate because nobody agreed what the allowance covered.

The fourth is the quiet one, and it is settled at signature by insisting each allowance carries a scope description rather than a title.

Why generous allowances are not generous

An owner offered a guaranteed maximum price with comfortable allowances should not read that as prudence.

A generous allowance does three things for the contractor. It reduces the chance of an overrun change order, which reduces friction. It increases the contract value, which increases fee where fee is a percentage. And where the underrun cannot fully return, it creates a pool of money inside the contract that will be spent on something.

None of that is improper and all of it is rational. But it means the owner cannot treat the allowance schedule as a conservative estimate. It is a set of positions, and each one has a direction.

The useful test at signature is to price three or four of the largest allowances independently, against the scope they are supposed to cover. The answers cluster into three groups: allowances that are clearly light and will produce change orders, allowances that are clearly heavy and will not fully return, and allowances that are about right.

The first group is a cost exposure. The second is a value leakage. Both are worth naming and they are named the same way, by reading the scope behind the number.

A worked example

Example only$640K

Illustrative figures. Not taken from any client project and not a quotation.

A 54 million dollar project carrying 31 allowances totaling $3.4 million.

At closeout, 19 allowances underspend by a total of $1.1 million and 12 overspend by a total of $460,000.

The contract permits netting within the allowance schedule. The net underrun is $640,000.

The contract also permits transfer of allowance underruns to the contractor contingency with notice. $400,000 is transferred during months fourteen through nineteen and is spent on coordination items that never appear as change orders.

The remaining $240,000 falls into the final cost of the work and is shared at the contractual 60 percent to the owner, returning $144,000.

The owner receives $144,000 of an original $1.1 million of underspend.

With owner consent required on transfers and netting limited to allowances within the same trade, the same project returns somewhere between $500,000 and $700,000. The difference was decided by two sentences nobody negotiated.

What to require at signature

Five requirements, all administrative, all cheap to agree before the contract is executed.

Every allowance carries a written scope description, not a title. Two lines is enough and it makes reconciliation possible.

Allowance status is reported monthly: carried, committed, spent, forecast at completion, per line. This is the single most useful monthly document on the project and it already exists inside the contractor cost system.

Netting between allowances requires owner consent. Not prohibition, consent.

Transfers from an allowance to contingency require owner consent.

Underruns return at one hundred percent rather than through the shared savings arithmetic, on the reasoning that an allowance was never a guaranteed price and its underrun was never a saving the contractor produced.

That last point is the one contractors argue about and it is the one worth holding, because it is also the most valuable.

Reading the schedule during the job, not at the end

Reconciliation at closeout is an accounting exercise. Reading the allowance schedule monthly is a forecasting exercise, and it is worth far more.

An allowance that is 80 percent committed with 40 percent of its scope remaining is a change order that will arrive in about four months. Knowing that in month nine means the scope can still be adjusted, a different product can be selected, or the exposure can be funded deliberately.

Knowing it in month eighteen means paying it.

The same schedule also shows the opposite. An allowance running well under with most of its scope committed is money that can be redirected while there is still something worth spending it on, rather than absorbed quietly at the end.

This is why the allowance line sits among the six numbers in the monthly report an owner should demand, and why the request for it belongs in the contract rather than in a conversation.

One further habit is worth building early. Every time an allowance is converted to a firm price, record what it was carried at and what it settled at, with a date. Over a job that produces a short list of thirty comparisons, and the pattern in it tells you whether the estimator who built the schedule was generally light, generally heavy, or reliable.

For an owner building repeatedly with the same contractor, that record is worth more than any single reconciliation, because it changes how the next allowance schedule is read before a dollar is committed.

What we do

We read every allowance against the scope behind it, price the three or four largest independently, and flag both directions: the ones that will overrun and the ones that will not come back. Then we write the five reconciliation requirements into the contract. That reading is a core part of the readiness review. After signature, monthly owner cost assurance keeps the same reading running against each payment application.

Questions people ask

Is netting always unfavorable to the owner?

Not always, and unrestricted netting is. Netting within a single trade, where an underrun and an overrun genuinely relate to the same scope, is reasonable and reduces administration. Netting across unrelated allowances converts thirty separate commercial positions into one number nobody can examine.

How many allowances is too many?

It depends less on the count than on the share of contract value. Above roughly eight percent, the guaranteed maximum price is carrying a lot of scope that has not been priced, and the guarantee covers less than it appears to. That is a finding about design readiness rather than about the allowances.

Can an allowance be converted to a fixed price later?

Yes, and it is usually the right move once the scope is defined. Converting an allowance to a firm number closes the position in both directions and removes it from the reconciliation entirely. The moment to do it is when the design is settled, not when the work is about to start.

Posted in Contingency and allowances Allowances Closeout Contract Owner

This is general information about construction contracts and is not legal advice.