Corven & Ashby, cost and risk advisory

What does a guaranteed maximum price guarantee?

GMP fundamentals

It guarantees a ceiling over one specific scope, described by one specific set of documents, on one specific date. That is the whole of it. What does a guaranteed maximum price guarantee beyond that? Nothing. The four mechanisms that move your cost do not touch the ceiling at all.

So what does a guaranteed maximum price guarantee, exactly

The contractor commits that the cost of the work, plus the fee, will not exceed a stated figure. If it does, the contractor absorbs the difference. That commitment is real and it is worth having.

The commitment is bounded by three things, and every one of them is written somewhere other than the amendment.

It is bounded by scope, meaning the drawings and specification identified by date and revision. It is bounded by qualifications, meaning the page of assumptions, exclusions and allowances near the back. It is bounded by time, meaning the conditions that existed when the price was built.

Change any one of those and the ceiling does not move. Your cost does, through change orders that sit above it.

This is not a trick and it is not unusual. A contractor cannot guarantee a price for work nobody has drawn. The problem is that owners read the amendment and assume the number covers the building they are imagining, rather than the building described in the documents attached.

The four mechanisms that move cost anyway

Allowances

Work that is inside the scope but not yet priced. The figure carried is an estimate. When the real number arrives and it is higher, the difference is yours. Allowances are not padding, they are unfinished decisions with a dollar sign attached.

Exclusions

Work the price does not cover, listed explicitly. Some exclusions are reasonable. Abatement on a building nobody has surveyed cannot be priced honestly. Others are quietly aggressive, excluding something clearly drawn on the plans.

Trade packages not yet bought out

A price built partly from estimates rather than awards. The gap between the two is the buyout gap. It can fall either way, and which way it falls decides whether contingency survives the first quarter.

The change pricing terms

What markup applies, to whose costs, at what rates, and how many days you have to respond. Fixed at signature and expensive to revisit afterwards. This is the ground covered by a review of the change and markup terms.

None of the four raises the guaranteed maximum price. All four raise what you pay.

What the ceiling is not

Three assumptions do most of the damage, and all three are reasonable if nobody has explained the mechanism.

It is not a fixed price. A lump sum on complete documents is closer to that. A guaranteed maximum price is a cap on cost plus fee, with the cost open to inspection and the cap attached to a scope that is often still moving. The open book is a real benefit and it is also the reason the number is provisional.

It is not a transfer of design risk. If the drawings and the specification disagree, somebody has to decide which one governs, and that decision usually costs money. The contractor priced what was drawn. Where the drawings are silent, nothing was priced, and silence is common on a package assembled while design continues.

It is not a promise about the schedule. The ceiling caps cost. Time sits in a different clause with different remedies, and a project can finish inside its guaranteed maximum price and four months late. Whether the date is achievable is a separate reading, covered by the schedule and procurement review.

None of this argues against the delivery method. It argues against reading the amendment on its own, which is what most owners do, because the amendment is the document that looks like the deal.

Where the definition actually lives

If the ceiling is defined by documents other than the amendment, those documents are what an owner has to read.

The qualifications page is the shortest document in the set and the most expensive. Every line on it is a boundary. Read it first.

The schedule of values shows how the number is built. Round figures, lines marked as allowances, and lines that look large for the work described are all worth a question.

The drawing and specification set is identified by date and revision for a reason. Anything issued after that date is a change unless the amendment says otherwise, and design does not usually stop while a price is being negotiated.

The contract form, usually AIA A133 with A102 on a CM at risk job, or a ConsensusDocs equivalent, sets who carries what. The amendments to the form matter more than the form.

The general conditions and general requirements cover what the general contractor charges for running the jobsite rather than building it. Supervision, trailers, hoisting, cleanup, temporary power. They are separate line items, they are often confused with each other, and on a long job they are large enough to deserve the same reading as the trade lines.

None of this requires construction experience. It requires the documents open at the same time, and somebody reading each one against the others rather than one after another.

A worked example

Example only$62M GMP

Illustrative figures. Not taken from any client project and not a quotation.

A guaranteed maximum price is set at $62,000,000. The owner reads the amendment, sees the number, and treats it as the cost of the building.

The qualifications page carries $4,340,000 in allowances, which is seven percent. Contractor contingency is $1,860,000, three percent. Nine trade packages are still estimates rather than awards.

Over the job the allowances land eighteen percent above the figures carried. That is $781,200. The buyout gap runs slightly against the owner on two packages and costs another $310,000.

Total movement above the carried figures: $1,091,200. Contingency is $1,860,000, so it absorbs the lot, and the guaranteed maximum price is never breached.

The contractor has honored the guarantee exactly. The owner has still spent the contingency by the time the first genuinely unforeseen condition appears, and there is nothing left to meet it.

Nothing here is misconduct. It is the mechanism working as written.

What to check before you sign

  1. List every allowance and ask for the resolution date on each one.
  2. Read the exclusions against the drawings and mark anything excluded that is also drawn.
  3. Confirm which drawing and specification set, by date and revision, the price is based on.
  4. Ask which trade packages are awarded and which are still estimates.
  5. Ask what contingency may be spent on, and who approves a draw.
  6. Fix the markup, the rates and the notice periods before signature, not after.

Where an answer arrives as a conversation rather than a document, write it down and attach it to the amendment. Nothing said in a meeting survives a change of personnel.

What we do

We read the package from the owner side and write down what the ceiling does not cover. Every finding cites the page it came from and carries the exposure behind it, ranked in dollars. The Pre-GMP Readiness Review covers the price and the qualifications page, and the other modules take the schedule, the scope gaps and the change mechanism. One call before your signing date, and no presentation deck. The rest of this subject sits in GMP fundamentals.

Questions people ask

Can a guaranteed maximum price be exceeded?

The ceiling itself is rarely exceeded, because change orders sit above it rather than inside it. An owner who signs a $62,000,000 price and pays $64,000,000 has usually not seen the guarantee fail. They have seen scope move, and every movement priced as a change against the owner rather than the contractor.

Is a GMP better than a lump sum for an owner?

It depends on how finished the design is. A lump sum on complete documents transfers more risk to the contractor. A GMP on incomplete documents gives an early number and an open book, at the cost of carrying the gaps yourself. Neither is safer in the abstract, and the qualifications page decides which you actually have.

How much of a GMP is typically carried as allowances?

There is no safe figure, and any number quoted without reading the documents is guesswork. What matters is not the percentage but whether each allowance names the work, carries a resolution date, and says who approves the figure when it lands. An allowance with no date is an open account.

Posted in GMP fundamentals GMP Ceiling Exclusions Contingency

This is general information about construction contracts and is not legal advice.