Corven & Ashby, cost and risk advisory

Construction lien waivers, and the tier nobody checks

Contracts and delivery methods

Construction lien waivers are the documents that stop an owner paying for the same work twice. An owner who pays the general contractor in full and receives no waivers from the tiers below has paid once and may be obliged to pay again, to parties it has never met and has no contract with.

Why an owner can be liable to someone it never hired

Mechanics lien statutes exist in every state and they share a common principle. A party that supplies labor or material improving real property has a claim against that property, whether or not it has a contract with the owner.

So a drywall subcontractor two tiers down, hired by a trade contractor who was hired by the general contractor, can file a lien against a building owned by somebody it has never dealt with.

The owner defense is not that it had no contract. The owner defense is that it paid, and that the money should have reached the lien claimant through the chain.

In several states that defense is strong where the owner paid properly and obtained waivers. In others it is weaker, and an owner can be required to pay twice for the same work where the general contractor received the money and did not pass it down.

Which is why the waiver chain matters, and why it matters at every tier rather than at the top.

The four kinds of construction lien waivers

Most states recognize four documents and mixing them up is the commonest administrative failure.

Conditional waiver on progress payment. Becomes effective only when the payment clears. This is what accompanies a current application.

Unconditional waiver on progress payment. Effective immediately, regardless of whether payment clears. Should only be given after funds are received, and should be collected for the previous period.

Conditional waiver on final payment. Effective when the final payment clears.

Unconditional waiver on final payment. Effective immediately and releases everything.

The correct monthly practice is conditional waivers with the current application and unconditional waivers for the previous one. An owner receiving only conditional waivers, month after month, has a chain of documents none of which has taken effect.

Several states prescribe statutory forms and a waiver that departs from the prescribed form may be ineffective, which is worth checking once at the start of a project rather than discovering during a dispute.

The tier problem

Owners routinely collect waivers from the general contractor and stop there.

That covers the exposure to the general contractor and none of the exposure below it, which is where almost all of the lien risk sits, because the general contractor is rarely the party that goes unpaid.

A workable practice sets a threshold. Waivers from every party above a stated contract value, at every tier, collected monthly with the application.

On a typical commercial project that is between thirty and sixty parties, and the general contractor already collects most of them for its own protection. The owner requirement is usually to receive copies rather than to create a new process.

Two additional documents make the chain checkable. A list of all parties above the threshold, updated as trades are awarded, and preliminary notices, which in many states must be served by parties intending to preserve lien rights and which therefore identify who is on the project.

Where an owner receives a preliminary notice from a party not on the list, that is worth a question, and it is usually the first sign of a subcontract the owner did not know about.

A worked example

Example only$1.6M

Illustrative figures. Not taken from any client project and not a quotation.

A 39 million dollar project. Waivers are collected from the general contractor monthly and from first tier trades above $250,000. Nothing is collected below that.

A mechanical trade contractor, paid in full through month fifteen, runs into difficulty on a different project and fails in month sixteen.

Its own subcontractors and suppliers, none of whom appeared in the waiver process, are owed $1.9 million for work already installed and already paid for by the owner.

Liens are filed against the property totaling $1.9 million. The owner has paid the general contractor, who has paid the mechanical contractor, who has not paid downward.

After negotiation and the general contractor own contribution, the owner funds $1.6 million to clear title, because the building is subject to a construction loan requiring clear title for the next drawdown.

Waivers at the second tier above a $100,000 threshold would have shown non payment from month thirteen, three months before the failure, when the general contractor could still have used joint check arrangements.

Joint checks, and when to use them

A joint check is issued payable to two parties together, typically a trade contractor and its supplier, so that the lower tier cannot be bypassed.

It is the standard remedy where there is doubt about whether money is reaching down the chain, and it is far more effective than any amount of correspondence.

Three situations justify it. A trade contractor showing financial stress, in the way described in subcontractor default. A lower tier party that has served a preliminary notice and is asking about payment. And any package where the supplier value is a large proportion of the trade value, such as equipment or fabricated material.

The right to require joint checks belongs in the contract at signature. Asked for in month sixteen it is a negotiation with a contractor who has no reason to agree and who reads the request as an accusation.

Owners who have the right frequently never use it. The value is in having it available on the month when the answer to a payment question is evasive.

The final waiver, and what it should cover

Final payment is the last moment an owner holds anything, and the waiver package at that point should be complete rather than representative.

Unconditional final waivers from every party above the threshold at every tier. A sworn statement from the general contractor listing all parties and confirming all are paid. And confirmation that no lien has been filed and no preliminary notice remains outstanding.

Owners sometimes release final payment against a general contractor waiver alone, on the basis that the general contractor has indemnified them. An indemnity from a party with no money left is not security, and the lien attaches to the property regardless.

The timing also matters. Lien filing periods in most states run for a set number of days after last furnishing of labor or material, commonly between sixty and one hundred and twenty. Releasing the last retainage before that period has run leaves the owner exposed with nothing held, which is why the retainage and waiver questions are really one question, as in construction retainage.

One further point on timing. Title insurance on the completed building, and any lender requirement for clear title at final drawdown, both depend on the lien position being closed. An owner that has released everything and then discovers an outstanding claim is negotiating from a position with no money and a deadline.

Where the lender requires clear title, the waiver package is not an administrative formality at all. It is a condition of getting paid.

What we do

We set the waiver threshold and the tier requirement at signature, check that the forms match what the relevant state prescribes, and secure the joint check right before it is needed. Monthly we check the waiver package against the party list rather than against the previous month. That work is part of the readiness review. After signature, monthly owner cost assurance keeps the same reading running against each payment application.

Questions people ask

Do lien rights vary much between states?

Considerably. Notice requirements, filing periods, priority rules and the effect of owner payment all differ, and some states protect a paying owner far more than others. The practical consequence is that the waiver process should be set up against the law of the state where the property sits, not from a template.

What threshold should apply?

Low enough to catch the parties that could file a meaningful lien and high enough to be administrable. Somewhere between fifty and a hundred thousand dollars works on most commercial projects, applied at every tier rather than only at the first, which is where the usual gap is.

Does a payment bond remove the need for waivers?

It changes the exposure substantially, because claimants generally look to the bond rather than to the property. It does not remove the administrative discipline, and on private work a payment bond is not always in place. Where one exists, the waiver process can reasonably be lighter.

Posted in Contracts and delivery methods Contracts Payment Liens Risk

This is general information about construction contracts and is not legal advice.