Corven & Ashby, cost and risk advisory

Construction retainage, and what it is actually securing

Contracts and delivery methods

Construction retainage is a percentage held back from every payment, usually five or ten percent, released at completion. It is the owner principal security for the entire project, and on most contracts the amount held falls below the cost of finishing the work at exactly the moment that cost becomes relevant.

What retainage is for

Three things, and owners frequently think of only the first.

Completing the work if the contractor does not. The classic purpose. If the contractor fails, the retainage funds part of the cost of somebody else finishing.

Securing the punch list and closeout. The practical purpose on almost every project, since outright contractor failure is rare and incomplete closeout is universal.

Maintaining commercial attention. The least discussed and arguably the most valuable. Money held is the reason a contractor returns to finish small items after the site team has moved on.

The third purpose explains why release timing matters more than the percentage. A contractor holding no retainage has no financial reason to prioritize a punch list on a building it has already left, and the phone stops being answered.

State law also intrudes here. Many states cap retainage percentages, several require it to be reduced at a stated point of completion, and some regulate the release timetable. Whatever the contract says, the statute in the relevant state governs, and it is worth knowing which applies before negotiating a figure that may not be enforceable.

The arithmetic that goes wrong

Retainage is a percentage of work completed, so it grows as the project progresses and peaks near completion.

The risk it secures does not follow the same curve. Early in a job, if the contractor fails, most of the work is still to be done and the remaining contract balance is large. There is a great deal of money left to fund completion.

Late in a job the remaining balance is small, the work left is the difficult finishing work, and the premium for a replacement contractor to complete somebody else building is at its highest.

So the exposure is worst exactly where the contract balance is thinnest, and retainage is the difference between the two.

A ten percent retainage on a project 95 percent complete secures roughly $6 million on a $60 million job, which is genuine protection. The same project with retainage reduced to five percent at halfway, as many contracts and several statutes provide, holds $3 million.

Whether $3 million is adequate depends entirely on what remains, and that is a calculation rather than a convention.

Reducing construction retainage at halfway, and whether to agree it

The common provision reduces construction retainage from ten percent to five once the project reaches fifty percent completion, or stops further retention entirely at that point.

The contractor argument for it is real. Retainage is expensive money, it is held from trade contractors too, and the cost of carrying it is inside the price somewhere.

The owner answer should not be a flat refusal. It should be a condition.

Reduction on satisfactory performance, assessed against stated criteria, is the workable middle. Schedule performance against the baseline, no outstanding claims, a clean safety record, and the buyout substantially complete.

That converts an automatic reduction into an earned one, and it gives the owner something to negotiate with at the exact midpoint of the job, which is otherwise the moment when it has least to work with.

Where the reduction is agreed unconditionally, the punch list security question described in substantial completion and the punch list becomes considerably more important, because there is less money left to hold.

A worked example

Example only$1.4M

Illustrative figures. Not taken from any client project and not a quotation.

A 58 million dollar project with ten percent retainage reducing to five at fifty percent completion, and release of all but double the punch list value at substantial completion.

At substantial completion the retainage held is $2.1 million. The punch list is priced by the contractor at $310,000, so $620,000 is retained and $1.48 million is released.

Over the following seven months the punch list proves to have been undervalued. The actual cost of completing outstanding items, including three trades that never return and are replaced, is $1.4 million.

The owner holds $620,000 and funds the balance.

The failure was not the percentage or the release schedule. It was accepting the contractor estimate of the punch list without an independent view, at the one moment when the number determined how much security remained.

An owner side pricing of that list, taking perhaps two days, would have set the retained figure at a level that covered the outcome.

Retainage down the chain

The owner holds retainage from the general contractor. The general contractor holds retainage from the trades. Those two are not the same and the difference is worth checking.

Where the general contractor releases trade retainage faster than the owner releases its own, the security behind each trade package is smaller than the headline figure suggests, and a trade that has been paid in full has no remaining commercial reason to return.

Several states also regulate this directly, requiring prompt payment down the chain and limiting how long a general contractor may hold trade retainage after the owner has released.

The useful question at signature is whether trade retainage mirrors prime retainage in both percentage and timing. Where it does not, the owner should understand which trades are fully paid and when, because those are the trades that will be hardest to bring back for closeout.

On a project where the envelope and the mechanical trades are released early, the two most likely sources of late defects are also the two with nothing left to hold.

The answer is not to hold trade retainage longer than the law allows, which in several states is not permitted. It is to know which trades are fully released and when, and to make sure the closeout security is sized against what remains outstanding on those specific packages.

That information comes from the payment applications, which carry the retainage position line by line, and it is one more reason to read them monthly rather than certify them, as in reviewing a payment application.

Alternatives to retainage

Retainage is not the only instrument and on some projects it is not the best one.

A retention bond. The contractor provides a surety bond in place of cash retention. The owner security becomes the surety rather than money held, which is stronger in a contractor failure and slower to realize.

An escrow arrangement. Retainage is held in an interest bearing account, with interest to the contractor. Reduces the carrying cost argument without reducing the security, and several states require this anyway.

A letter of credit. Common on larger projects. Immediate to draw on, expensive for the contractor to provide, and it ties up their credit facility.

Line item release. Retainage on each trade released when that trade is genuinely complete rather than at project milestones. Administratively heavier and much better aligned with the actual risk.

The last one is the most underused. It keeps money against the trades that are still working and releases it from those that are genuinely finished, which is what retainage was supposed to do in the first place.

What we do

We read the retainage provisions against the statute in the relevant state, check whether trade retainage mirrors the prime, and condition any midpoint reduction on stated performance criteria. At substantial completion we value the punch list independently before the release is calculated. That work is part of the readiness review. After signature, monthly owner cost assurance keeps the same reading running against each payment application.

Questions people ask

Is five or ten percent the right figure?

It depends on the state, the contractor and what alternative security exists. Ten percent is conventional at the start and is capped or restricted by statute in a number of states. The figure matters far less than the release schedule and whether anything secures the closeout period.

Should retainage be held on stored materials?

Generally yes, and at the same rate, since materials delivered but not installed represent no completed work. What matters more is whether the contract requires proof of title, adequate insurance and secure storage before paying for them at all, which is where the real exposure on stored materials sits.

When can an owner withhold beyond retainage?

Where the contract provides for it, typically for defective work, failure to pay subcontractors, or damage caused by the contractor. Those rights are worth reading before they are needed, because the notice requirements attached to them are usually short and the remedy is lost if they are missed.

Posted in Contracts and delivery methods Contracts Payment Security Owner

This is general information about construction contracts and is not legal advice.